MCCOOK

Substation

Nebraska · MCCOOK PUBLIC POWER DISTRICT

Max voltage
115
kV

MCCOOK is an electric transmission substation in Nebraska, operated by MCCOOK PUBLIC POWER DISTRICT. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorMCCOOK PUBLIC POWER DISTRICT
Co-ownerNEBRASKA PUBLIC POWER DISTRICT
Coordinates40.2216, -100.6508

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#85115 kVMCCOOK PUBLIC POWER DISTRICTIN SERVICE7.2 mi
#39561115 kVNEBRASKA PUBLIC POWER DISTRICTIN SERVICE28.1 mi
#45001115 kVNEBRASKA PUBLIC POWER DISTRICTIN SERVICE9.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of MCCOOK, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near MCCOOK substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN119601Substation-AdjacentKSDecatur County115 kV100 MW3.5 yrs64.7
UNKNOWN119603Substation-AdjacentKSDecatur County115 kV100 MW3.5 yrs64.4
Greenfield (RED WILLOW - MINGO)GreenfieldNERed Willow County345 kV600 MW3.5 yrs63.3
RED WILLOWSubstation-AdjacentNEHayes County345 kV600 MW3.5 yrs62.4
Greenfield (RED WILLOW - MINGO)GreenfieldNERed Willow County345 kV600 MW3.5 yrs62.3
Greenfield (GENTLEMAN - RED WILLOW)GreenfieldNEHayes County345 kV600 MW3.5 yrs62.1
TAP140617Substation-AdjacentKSDecatur County115 kV100 MW3.5 yrs62.0
MCCOOKSubstation-AdjacentNERed Willow County115 kV100 MW3.5 yrs62.0

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for MCCOOK substation, Nebraska. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.