YAAK

Substation

Montana · BONNEVILLE POWER ADMINISTRATION

Max voltage
115
kV

YAAK is an electric transmission substation in Montana, operated by BONNEVILLE POWER ADMINISTRATION. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorBONNEVILLE POWER ADMINISTRATION
StateMontana
Coordinates48.5996, -115.9877

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#68260115 kVBONNEVILLE POWER ADMINISTRATION17.9 mi
#68261115 kVBONNEVILLE POWER ADMINISTRATION12.4 mi
#69523115 kVBONNEVILLE POWER ADMINISTRATION11.6 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of YAAK, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near YAAK substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
TAP206879Substation-AdjacentIDBoundary County138 kV100 MW2.0 yrs65.7
TROYSubstation-AdjacentMTLincoln County115 kV100 MW1.1 yrs65.0
TAP206878Substation-AdjacentIDBoundary County138 kV100 MW2.0 yrs63.3
YAAKSubstation-AdjacentMTLincoln County115 kV100 MW1.1 yrs63.1
Greenfield (TROY - LIBBY)GreenfieldMTLincoln County115 kV100 MW1.1 yrs61.9
Greenfield (YAAK - TAP203504)GreenfieldMTLincoln County115 kV100 MW1.1 yrs61.8
TAP204956Substation-AdjacentIDBoundary County115 kV100 MW2.0 yrs61.7
UNKNOWN207654Substation-AdjacentIDBoundary County115 kV100 MW2.0 yrs61.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for YAAK substation, Montana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.