TAP149932

Substation

Mississippi · ALABAMA POWER CO

Max voltage
161
kV

TAP149932 is an electric transmission substation in Mississippi, operated by ALABAMA POWER CO. It is classified as sub-transmission (138 kv) and connects 2 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage161 kV
Min voltage161 kV
Voltage classSub-transmission (138 kV)
Connected lines2

Ownership & operation

OperatorALABAMA POWER CO
Coordinates34.4496, -88.0998

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#331161 kVALABAMA POWER COIN SERVICE9.7 mi
#20750161 kVALABAMA POWER COIN SERVICE0.1 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP149932, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP149932 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
BROWNS FERRYSubstation-AdjacentALMarion County500 kV1,000 MW1.4 yrs73.6
ColbertBrownfieldALColbert1,350 MW72.0
Greenfield (WESTPOINT - BROWNS FERRY)GreenfieldALMarion County500 kV1,000 MW1.4 yrs68.6
PICKWICK LANDING DAMSubstation-AdjacentALColbert County161 kV100 MW3.7 yrs68.5
Greenfield (UNION - BROWNS FERRY)GreenfieldMSTishomingo County500 kV1,000 MW1.4 yrs68.2
Greenfield (UNION - BROWNS FERRY)GreenfieldMSTishomingo County500 kV1,000 MW1.4 yrs67.8
Greenfield (WESTPOINT - BROWNS FERRY)GreenfieldALMarion County500 kV1,000 MW1.4 yrs67.1
TAP150113Substation-AdjacentALMarion County161 kV100 MW3.7 yrs67.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP149932 substation, Mississippi. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.