WEBRE
SubstationLouisiana · ENTERGY LOUISIANA LLC
WEBRE is an electric transmission substation in Louisiana, operated by ENTERGY LOUISIANA LLC. It is classified as extra-high-voltage (500 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #7538 | 500 kV | ENTERGY LOUISIANA LLC | IN SERVICE | 25.2 mi |
| #20608 | 500 kV | ENTERGY LOUISIANA LLC | IN SERVICE | 26.5 mi |
| #30423 | 500 kV | ENTERGY LOUISIANA LLC | IN SERVICE | 39.7 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of WEBRE, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| UNKNOWN112483 | Substation-Adjacent | LA | West Baton Rouge Parish | 230 kV | 300 MW | 1.4 yrs | 71.8 |
| BIG CAJUN 2 | Substation-Adjacent | LA | West Baton Rouge Parish | 500 kV | 1,000 MW | 1.4 yrs | 71.1 |
| UNKNOWN112489 | Substation-Adjacent | LA | Iberville Parish | 230 kV | 300 MW | 1.4 yrs | 70.8 |
| FANCY POINT | Substation-Adjacent | LA | West Feliciana Parish | 500 kV | 1,000 MW | 1.4 yrs | 70.0 |
| WELLS | Substation-Adjacent | LA | St. Landry Parish | 500 kV | 1,000 MW | 1.4 yrs | 69.8 |
| WEBRE | Substation-Adjacent | LA | Pointe Coupee Parish | 500 kV | 1,000 MW | 1.4 yrs | 69.4 |
| UNKNOWN112426 | Substation-Adjacent | LA | Pointe Coupee Parish | 230 kV | 300 MW | 1.4 yrs | 69.0 |
| BEADLE | Substation-Adjacent | LA | Lafayette Parish | 230 kV | 300 MW | 1.4 yrs | 68.8 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for WEBRE substation, Louisiana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.