TAP150012

Substation

Louisiana · ENTERGY LOUISIANA INC

Max voltage
115
kV

TAP150012 is an electric transmission substation in Louisiana, operated by ENTERGY LOUISIANA INC. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorENTERGY LOUISIANA INC
Coordinates32.5539, -92.6245

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#579115 kVENTERGY LOUISIANA INCIN SERVICE1.1 mi
#38136115 kVENTERGY LOUISIANA INCIN SERVICE3.5 mi
#45363115 kVENTERGY LOUISIANA INCIN SERVICE0.0 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP150012, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP150012 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
MOUNT OLIVESubstation-AdjacentLALincoln Parish500 kV1,000 MW1.4 yrs72.8
Greenfield (MOUNT OLIVE - UNKNOWN157576)GreenfieldLABienville Parish500 kV1,000 MW1.4 yrs64.8
Greenfield (MOUNT OLIVE - UNKNOWN157576)GreenfieldLABienville Parish500 kV1,000 MW1.4 yrs64.4
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)GreenfieldARUnion County500 kV1,000 MW1.4 yrs63.6
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)GreenfieldLALincoln Parish500 kV1,000 MW1.4 yrs63.2
UNKNOWN116921Substation-AdjacentLALincoln Parish115 kV100 MW1.4 yrs63.0
Greenfield (MOUNT OLIVE - EL DORADO SUBSTA)GreenfieldLALincoln Parish500 kV1,000 MW1.4 yrs62.8
Greenfield (MOUNT OLIVE - UNKNOWN157576)GreenfieldLABienville Parish500 kV1,000 MW1.4 yrs62.8

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP150012 substation, Louisiana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.