RICHARD
SubstationLouisiana · CLECO COR
RICHARD is an electric transmission substation in Louisiana, operated by CLECO COR. It is classified as extra-high-voltage (500 kv) and connects 13 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Ownership & operation
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #27085 | 500 kV | — | IN SERVICE | 16.3 mi |
| #34300 | 500 kV | ENTERGY LOUISIANA LLC | IN SERVICE | 59.4 mi |
| #22090 | 230 kV | CLECO COR | IN SERVICE | 30.5 mi |
| #32583 | 138 kV | ENTERGY | IN SERVICE | 10.7 mi |
| #39677 | 138 kV | ENTERGY | IN SERVICE | 0.3 mi |
| #40207 | 138 kV | ENTERGY | IN SERVICE | 11.3 mi |
| #42361 | 138 kV | ENTERGY | IN SERVICE | 22.7 mi |
| #43186 | 138 kV | ENTERGY | IN SERVICE | 0.3 mi |
| #44903 | 138 kV | ENTERGY | IN SERVICE | 5.6 mi |
| #7309 | 138 kV | ENTERGY | IN SERVICE | 28.3 mi |
| #47044 | 138 kV | ENTERGY | IN SERVICE | 6.1 mi |
| #30448 | 138 kV | ENTERGY | IN SERVICE | 13.2 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of RICHARD, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| WEST FORK | Substation-Adjacent | LA | St. Landry Parish | 230 kV | 300 MW | 1.4 yrs | 66.7 |
| UNKNOWN116010 | Substation-Adjacent | LA | Lafayette Parish | 230 kV | 300 MW | 1.4 yrs | 65.5 |
| UNKNOWN116078 | Substation-Adjacent | LA | Lafayette Parish | 138 kV | 100 MW | 1.4 yrs | 65.5 |
| MEAUX | Substation-Adjacent | LA | Lafayette Parish | 230 kV | 300 MW | 1.4 yrs | 65.3 |
| UNKNOWN116114 | Substation-Adjacent | LA | St. Landry Parish | 138 kV | 100 MW | 1.4 yrs | 65.2 |
| UNKNOWN149796 | Substation-Adjacent | LA | Evangeline Parish | 138 kV | 100 MW | 1.4 yrs | 64.9 |
| UNKNOWN112464 | Substation-Adjacent | LA | Lafayette Parish | 138 kV | 100 MW | 1.4 yrs | 64.8 |
| UNKNOWN112419 | Substation-Adjacent | LA | St. Landry Parish | 138 kV | 100 MW | 1.4 yrs | 64.7 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for RICHARD substation, Louisiana. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.