TAP149317
SubstationKansas · MIDWEST ENERGY INC
TAP149317 is an electric transmission substation in Kansas, operated by MIDWEST ENERGY INC. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #7802 | 115 kV | MIDWEST ENERGY INC | IN SERVICE | 4.7 mi |
| #12413 | 115 kV | MIDWEST ENERGY INC | IN SERVICE | 0.0 mi |
| #34461 | 115 kV | MIDWEST ENERGY INC | IN SERVICE | 17.1 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of TAP149317, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| UNKNOWN119927 | Substation-Adjacent | KS | Russell County | 115 kV | 100 MW | 3.5 yrs | 67.9 |
| UNKNOWN149146 | Substation-Adjacent | KS | Rice County | 230 kV | 300 MW | 3.5 yrs | 67.9 |
| UNKNOWN118148 | Substation-Adjacent | KS | Ellsworth County | 230 kV | 300 MW | 3.5 yrs | 67.0 |
| UNKNOWN119925 | Substation-Adjacent | KS | Russell County | 115 kV | 100 MW | 3.5 yrs | 66.1 |
| Greenfield (UNKNOWN118148 - KNOLL) | Greenfield | KS | Russell County | 230 kV | 300 MW | 3.5 yrs | 64.7 |
| Greenfield (UNKNOWN118148 - KNOLL) | Greenfield | KS | Russell County | 230 kV | 300 MW | 3.5 yrs | 64.6 |
| TAP149317 | Substation-Adjacent | KS | Russell County | 115 kV | 100 MW | 3.5 yrs | 64.5 |
| UNKNOWN119897 | Substation-Adjacent | KS | Ellsworth County | 115 kV | 100 MW | 3.5 yrs | 64.4 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen