TAP207279

Substation

Idaho · IDAHO POWER CO

Max voltage
138
kV

TAP207279 is an electric transmission substation in Idaho, operated by IDAHO POWER CO. It is classified as sub-transmission (138 kv) and connects 4 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage138 kV
Min voltage138 kV
Voltage classSub-transmission (138 kV)
Connected lines4

Ownership & operation

OperatorIDAHO POWER CO
StateIdaho
Coordinates42.9043, -112.5431

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#70139138 kVIDAHO POWER CO11.1 mi
#74871138 kVIDAHO POWER CO0.2 mi
#74968138 kVIDAHO POWER CO1.6 mi
#74969138 kVIDAHO POWER CO0.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP207279, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP207279 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
KINPORTSubstation-AdjacentIDPower County345 kV600 MW2.0 yrs70.2
BRADYSubstation-AdjacentIDPower County230 kV300 MW2.0 yrs70.1
BORAHSubstation-AdjacentIDPower County345 kV600 MW2.0 yrs69.8
FREMONTSubstation-AdjacentIDBannock County161 kV100 MW2.0 yrs67.7
TAP205291Substation-AdjacentIDBannock County138 kV100 MW2.0 yrs67.5
HOKUSubstation-AdjacentIDBannock County138 kV100 MW2.0 yrs67.3
TAP204737Substation-AdjacentIDBannock County138 kV100 MW2.0 yrs67.3
POWER COUNTY WIND PARK SOUTHSubstation-AdjacentIDPower County230 kV300 MW2.0 yrs67.1

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP207279 substation, Idaho. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.