BRADY

Substation

Idaho · IDAHO POWER CO

Max voltage
230
kV

BRADY is an electric transmission substation in Idaho, operated by IDAHO POWER CO. It is classified as high-voltage (230 kv) and connects 9 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage230 kV
Min voltage138 kV
Voltage classHigh-voltage (230 kV)
Connected lines9

Ownership & operation

OperatorIDAHO POWER CO
StateIdaho
Coordinates42.7730, -112.8703

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#70194230 kVIDAHO POWER CO18.1 mi
#70178230 kVIDAHO POWER CO56.5 mi
#70184230 kVIDAHO POWER CO4.0 mi
#70190230 kVIDAHO POWER CO4.0 mi
#70191230 kVIDAHO POWER CO7.3 mi
#70193230 kVIDAHO POWER CO18.2 mi
#70242138 kVIDAHO POWER CO6.1 mi
#70195138 kVIDAHO POWER CO0.4 mi
#70151138 kVIDAHO POWER CO18.2 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of BRADY, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near BRADY substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
KINPORTSubstation-AdjacentIDPower County345 kV600 MW2.0 yrs70.2
BRADYSubstation-AdjacentIDPower County230 kV300 MW2.0 yrs70.1
BORAHSubstation-AdjacentIDPower County345 kV600 MW2.0 yrs69.8
FREMONTSubstation-AdjacentIDBannock County161 kV100 MW2.0 yrs67.7
HOKUSubstation-AdjacentIDBannock County138 kV100 MW2.0 yrs67.3
POWER COUNTY WIND PARK SOUTHSubstation-AdjacentIDPower County230 kV300 MW2.0 yrs67.1
SUNBEAMSubstation-AdjacentIDPower County230 kV300 MW2.0 yrs66.8
PINGREESubstation-AdjacentIDBingham County138 kV100 MW2.0 yrs66.8

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for BRADY substation, Idaho. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.