CORDOVA
SubstationArkansas · TENNESSEE VALLEY AUTHORITY
CORDOVA is an electric transmission substation in Arkansas, operated by TENNESSEE VALLEY AUTHORITY. It is classified as extra-high-voltage (500 kv) and connects 20 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.
Voltage & classification
Connected transmission lines
Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.
| Line ID | Voltage | Owner | Status | Length |
|---|---|---|---|---|
| #14379 | 500 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 26.9 mi |
| #29069 | 500 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 20.9 mi |
| #24190 | 500 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 42.2 mi |
| #59283 | 500 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 23.3 mi |
| #59284 | 500 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 40.6 mi |
| #21626 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 9.5 mi |
| #23574 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 15.0 mi |
| #23663 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 10.1 mi |
| #3178 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 14.0 mi |
| #27055 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 3.8 mi |
| #27361 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 7.1 mi |
| #41353 | 161 kV | TENNESSEE VALLEY AUTHORITY | IN SERVICE | 7.2 mi |
Nearby datacenter candidate sites
Scored candidate sites within roughly 25 miles of CORDOVA, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.
| Site | Type | State | County | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|---|---|
| FREEPORT | Substation-Adjacent | MS | DeSoto County | 500 kV | 1,000 MW | 1.4 yrs | 78.6 |
| BROWNSVILLE | Substation-Adjacent | TN | Shelby County | 500 kV | 1,000 MW | 1.4 yrs | 78.1 |
| CORDOVA | Substation-Adjacent | TN | Shelby County | 500 kV | 1,000 MW | 1.4 yrs | 77.6 |
| SOUTHAVEN | Substation-Adjacent | MS | DeSoto County | 500 kV | 1,000 MW | 1.4 yrs | 75.9 |
| UNKNOWN175599 | Substation-Adjacent | TN | Tipton County | 500 kV | 1,000 MW | 1.4 yrs | 75.9 |
| SHELBY | Substation-Adjacent | TN | Tipton County | 500 kV | 1,000 MW | 1.4 yrs | 75.5 |
| HORN LAKE | Substation-Adjacent | MS | DeSoto County | 230 kV | 300 MW | 1.4 yrs | 74.3 |
| Greenfield (FREEPORT - CORDOVA) | Greenfield | TN | Shelby County | 500 kV | 1,000 MW | 1.4 yrs | 73.9 |
Dataset updated . Screening estimates derived from public data sources.
Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.
Go deeper than the public screen
This page shows a public slice of the GridCensus dataset for CORDOVA substation, Arkansas. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.