TAP142784

Substation

Alabama · ALABAMA POWER CO

Max voltage
115
kV

TAP142784 is an electric transmission substation in Alabama, operated by ALABAMA POWER CO. It is classified as sub-transmission (115 kv) and connects 3 transmission lines. Substation proximity is one of the strongest speed-to-power signals for siting a datacenter — interconnection distance to an energized, high-voltage bus is often the binding constraint on time-to-energization.

Voltage & classification

Max voltage115 kV
Min voltage115 kV
Voltage classSub-transmission (115 kV)
Connected lines3

Ownership & operation

OperatorALABAMA POWER CO
StateAlabama
Coordinates30.2852, -87.5826

Connected transmission lines

Lines terminating at or passing through this substation, by HIFLD line ID, highest voltage first.

Line IDVoltageOwnerStatusLength
#1792115 kVALABAMA POWER COIN SERVICE1.5 mi
#4648115 kVALABAMA POWER COIN SERVICE0.5 mi
#23813115 kVALABAMA POWER COIN SERVICE2.3 mi

Browse the full transmission-line map →

Nearby datacenter candidate sites

Scored candidate sites within roughly 25 miles of TAP142784, ranked by DC Readiness. Sites this close to an energized substation carry a strong speed-to-power advantage.

Candidate sites near TAP142784 substation
SiteTypeStateCountyVoltageCapacityQueue waitScore
UNKNOWN157814Substation-AdjacentFLEscambia County230 kV300 MW3.7 yrs70.1
BRENTWOODSubstation-AdjacentFLEscambia County230 kV300 MW3.7 yrs69.6
BELLVIEWSubstation-AdjacentFLEscambia County230 kV300 MW3.7 yrs69.6
SILVERHILLSubstation-AdjacentALBaldwin County230 kV300 MW3.7 yrs69.0
UNKNOWN109094Substation-AdjacentALBaldwin County230 kV300 MW3.7 yrs67.2
BEULAHSubstation-AdjacentFLEscambia County230 kV300 MW3.7 yrs66.1
TAP168993Substation-AdjacentALBaldwin County115 kV100 MW3.7 yrs65.9
SCENIC HILLSSubstation-AdjacentFLEscambia County115 kV100 MW3.7 yrs65.7

Dataset updated . Screening estimates derived from public data sources.

Substation attributes are derived from public HIFLD / EIA infrastructure data and may lag real-world upgrades or retirements. Voltage and connected-line counts are screening figures — confirm available capacity and interconnection terms directly with the operating utility and ISO.

Go deeper than the public screen