CLOVERDALE 765KV

Substation-Adjacent

SALEM (CITY), Virginia · PJM

DC Readiness
73.9
Excellent / 100

CLOVERDALE 765KV is a substation-adjacent datacenter candidate site in SALEM (CITY), Virginia, interconnecting through PJM. It screens at 73.9/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationCLOVERDALE 765KV
Substation distance0.0 mi
Substation voltage765 kV
Available capacity1,000 MW
LMP zonePJM_APS
Wholesale LMP$43.66/MWh

Speed to power

ISO / RTO regionPJM
Queue depth118
Avg queue wait3.0 yrs
Recent queue wait4.0 yrs
Completion rate23%
Withdrawal rate77%

Connectivity

Nearest IXPCitynet Charleston
IXP distance112.2 mi
Fiber providers3
Fiber coverage84.3%
Nearest cloud providerAzure
Nearest cloud regioneastus
Cloud region distance19.0 mi

Site characteristics

Parcel ownerAPPALACHIAN POWER CO
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score70/100
Construction cost index87.4 (avg 100)

Location context

Nearest datacenterLumos Networks
DC distance55.3 mi
Nearest rail0.7 mi
Nearest gas pipeline3.5 mi
Nearest fiber route91.3 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Cooling degree days1,300
Heating degree days4,000
Land price / acre$5,900

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
53
Fiber connectivity12%
72
Energy cost10%
82
Water risk8%
88
Natural hazard8%
70
Buildability7%
45
Labor market4%
50
DC cluster4%
55
Land / acreage3%
61
Construction cost3%
77
Gas pipeline2%
89
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in SALEM (CITY), ranked by DC Readiness.

Sites near CLOVERDALE 765KV
SiteTypeVoltageCapacityQueue waitScore
MATT FUNKSubstation-Adjacent345 kV600 MW3.0 yrs71.4
Greenfield (CLOVERDALE 765KV - JACKSONS FE)Greenfield765 kV1,000 MW3.0 yrs68.6
BENT MOUNTAINSubstation-Adjacent138 kV100 MW3.0 yrs68.4
POAGES MILLSubstation-Adjacent138 kV100 MW3.1 yrs67.4
WEST SALEMSubstation-Adjacent138 kV100 MW3.0 yrs66.6
Greenfield (CLOVERDALE - MATT FUNK)Greenfield345 kV600 MW3.0 yrs63.2
HANCOCKSubstation-Adjacent138 kV100 MW3.0 yrs60.1
OZ SalemGreenfield3.1 yrs59.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for CLOVERDALE 765KV, SALEM (CITY). Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.