Skip to content
Gridcensus

Goochland County, Virginia · PJM

DC Readiness
59.4
Good / 100

NORTH POLE is a substation-adjacent datacenter candidate site in Goochland County, Virginia, interconnecting through PJM. It screens at 59.4/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 3.8 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationNORTH POLE
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW

Speed to power

ISO / RTO regionPJM
Queue depth878
Avg queue wait3.8 yrs

Connectivity

Nearest IXPEdgeConneX Richmond (EDCRIC01)
IXP distance17.8 mi
Fiber providers4
Fiber coverage37.2%

Site characteristics

Risk & environment

Water stress (WRI)Low
Wetlands (NWI)
Critical habitat
Superfund nearby
Hazard sub-score70/100

Location context

Nearest datacenterEdgeConneX Richmond (EDCRIC01)
DC distance17.8 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity7.98¢/kWh
Industrial electricity6.17¢/kWh
Cooling degree days1,300
Heating degree days4,000
Land price / acre$7,139

Incentive detail: Sales tax exemption on DC equipment for $150M+ investments (2025: $100M+); MEGA site program.

Site location

◆ Loading map…
≥ 7560–7540–60≤ 40
This site + 8 nearby

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
38
Fiber connectivity12%
47
Energy cost10%
50
Water risk8%
88
Natural hazard8%
70
Buildability7%
60
Labor market4%
50
DC cluster4%
60
Land / acreage3%
46
Construction cost3%
50
Gas pipeline2%
10
Tax incentive2%
100
Climate / cooling2%
60

Nearby comparable sites

Other scored datacenter candidate sites in Goochland County, ranked by DC Readiness.

Sites near NORTH POLE
SiteTypeVoltageCapacityQueue waitScore
West Creek Campus 4: Oak HillShovel-Ready3.8 yrs53.7
West Creek Campus 3Shovel-Ready3.8 yrs53.7
West Creek Campus 5Shovel-Ready3.8 yrs53.7
West Creek Campus 2Shovel-Ready3.8 yrs53.6
West Creek Campus 7Shovel-Ready3.8 yrs53.5
0 Three Chopt RoadShovel-Ready3.8 yrs53.3
Waters Edge BuildingShovel-Ready3.8 yrs53.2
Manakin Trade CenterShovel-Ready3.8 yrs53.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for NORTH POLE, Goochland County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.