UNKNOWN301314

Substation-Adjacent

Fannin County, Texas · ERCOT

DC Readiness
70.2
Excellent / 100

UNKNOWN301314 is a substation-adjacent datacenter candidate site in Fannin County, Texas, interconnecting through ERCOT. It screens at 70.2/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN301314
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zoneERCOT_NORTH
Wholesale LMP$16.22/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPScaleMatrix Dallas Data Center US-South 01
IXP distance38.3 mi
Fiber providers6
Fiber coverage34.9%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance64.4 mi

Site characteristics

Parcel ownerONCOR ELECTRIC DELIVERY CO.
Land owner typeprivate
Buildability85.0/100
Land cover (NLCD)Barren Land

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index77.3 (avg 100)

Location context

Nearest datacenterChoctaw Nation of Oklahoma Data Center
DC distance23.6 mi
Nearest rail0.8 mi
Nearest gas pipeline0.6 mi
Nearest fiber route27.1 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.35¢/kWh
Industrial electricity27.59¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$3,952

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
59
Fiber connectivity12%
60
Energy cost10%
92
Water risk8%
64
Natural hazard8%
45
Buildability7%
85
Labor market4%
50
DC cluster4%
70
Land / acreage3%
49
Construction cost3%
86
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Fannin County, ranked by DC Readiness.

Sites near UNKNOWN301314
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN302406Substation-Adjacent345 kV600 MW3.4 yrs68.2
JOHNSONSubstation-Adjacent345 kV600 MW3.4 yrs67.5
UNKNOWN303249Substation-Adjacent345 kV600 MW3.4 yrs67.3
UNKNOWN304272Substation-Adjacent138 kV100 MW3.4 yrs64.2
Greenfield (FARMERSVILLE - UNKNOWN302406)Greenfield345 kV600 MW3.4 yrs63.6
TAP308058Substation-Adjacent138 kV100 MW3.4 yrs63.0
Greenfield (UNKNOWN300188 - UNKNOWN303249)Greenfield345 kV600 MW3.4 yrs62.9
UNKNOWN303945Substation-Adjacent138 kV100 MW3.4 yrs62.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.