UNKNOWN303329

Substation-Adjacent

Ellis County, Texas · ERCOT

DC Readiness
66.4
Good / 100

UNKNOWN303329 is a substation-adjacent datacenter candidate site in Ellis County, Texas, interconnecting through ERCOT. It screens at 66.4/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN303329
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zoneERCOT_CENTRAL
Wholesale LMP$18.75/MWh
Utility commercial rate0.17¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPDataBank Dallas (DFW1)
IXP distance23.7 mi
Fiber providers18
Fiber coverage52.1%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance23.6 mi

Site characteristics

Parcel ownerONCOR ELECTRIC DELIVERY CO.
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteOWENS CORNING INSULATING SYSTEMS WAXAHACHIE PLANT
Hazard sub-score35/100
Construction cost index90.0 (avg 100)

Location context

Nearest datacenterCompass Data Center
DC distance7.5 mi
Nearest rail0.2 mi
Nearest gas pipeline2.2 mi
Nearest fiber route23.5 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity17.02¢/kWh
Industrial electricity6.84¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$5,374

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
59
Fiber connectivity12%
71
Energy cost10%
92
Water risk8%
60
Natural hazard8%
35
Buildability7%
100
Labor market4%
50
DC cluster4%
95
Land / acreage3%
62
Construction cost3%
75
Gas pipeline2%
93
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Ellis County, ranked by DC Readiness.

Sites near UNKNOWN303329
SiteTypeVoltageCapacityQueue waitScore
VENUSSubstation-Adjacent345 kV600 MW3.4 yrs73.3
DESOTO SWSubstation-Adjacent345 kV600 MW3.4 yrs73.0
UNKNOWN308252Substation-Adjacent345 kV600 MW3.4 yrs71.9
UNKNOWN307180Substation-Adjacent138 kV100 MW3.4 yrs67.0
UNKNOWN304110Substation-Adjacent138 kV100 MW3.4 yrs66.8
MIDLOTHIAN ENERGY FACILITYSubstation-Adjacent345 kV600 MW3.4 yrs66.8
UNKNOWN301892Substation-Adjacent138 kV100 MW3.4 yrs66.7
Greenfield (VENUS - LIGGETT)Greenfield345 kV600 MW3.4 yrs66.5

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN303329, Ellis County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.