UNKNOWN309367

Substation-Adjacent

Brazoria, Texas · ERCOT

DC Readiness
60.7
Good / 100

UNKNOWN309367 is a substation-adjacent datacenter candidate site in Brazoria, Texas, interconnecting through ERCOT. It screens at 60.7/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN309367
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zoneERCOT_HOUSTON
Wholesale LMP$18.71/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPDatabank Houston Galleria (HOU5)
IXP distance47.1 mi
Fiber providers11
Fiber coverage68.0%
Nearest cloud providerAzure
Nearest cloud regionsouthcentralus
Cloud region distance177.5 mi

Site characteristics

Parcel ownerTEXAS-NEW MEXICO POWER CO.
Land owner typeprivate
Buildability75.0/100
Land cover (NLCD)Pasture/Hay

Risk & environment

Flood zoneZone X
Water stress (WRI)2.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score45/100
Construction cost index120.0 (avg 100)

Location context

Nearest datacenterRice Data Center
DC distance42.4 mi
Nearest rail1.0 mi
Nearest gas pipeline0.7 mi
Nearest fiber route73.9 mi
County hazard (FEMA NRI)Very High (55)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.07¢/kWh
Industrial electricity6.04¢/kWh
Cooling degree days2,600
Heating degree days1,800
Land price / acre$5,440

Incentive detail: Chapter 313/Chapter 403 property tax abatements; Texas Enterprise Fund; no state income tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
59
Fiber connectivity12%
69
Energy cost10%
90
Water risk8%
44
Natural hazard8%
45
Buildability7%
75
Labor market4%
50
DC cluster4%
45
Land / acreage3%
47
Construction cost3%
50
Gas pipeline2%
98
Tax incentive2%
100
Climate / cooling2%
0

Nearby comparable sites

Other scored datacenter candidate sites in Brazoria, ranked by DC Readiness.

Sites near UNKNOWN309367
SiteTypeVoltageCapacityQueue waitScore
DOW VELASCOSubstation-Adjacent345 kV600 MW3.4 yrs69.5
TAP302748Substation-Adjacent345 kV600 MW3.4 yrs68.1
UNKNOWN302859Substation-Adjacent138 kV100 MW3.4 yrs64.8
MEADOWSubstation-Adjacent345 kV600 MW3.4 yrs64.2
UNKNOWN310390Substation-Adjacent138 kV100 MW3.4 yrs64.1
BIPORTSubstation-Adjacent138 kV100 MW3.4 yrs63.2
HOFMANSubstation-Adjacent138 kV100 MW3.4 yrs63.1
Greenfield (DOW VELASCO - OASIS)Greenfield345 kV600 MW3.4 yrs63.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN309367, Brazoria. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.