UNKNOWN118766

Substation-Adjacent

Bryan County, Oklahoma · ERCOT

DC Readiness
63.0
Good / 100

UNKNOWN118766 is a substation-adjacent datacenter candidate site in Bryan County, Oklahoma, interconnecting through ERCOT. It screens at 63.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN118766
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zoneERCOT_NORTH
Wholesale LMP$16.22/MWh
Utility commercial rate0.10¢/kWh

Speed to power

ISO / RTO regionERCOT
Queue depth876
Avg queue wait3.4 yrs
Recent queue wait3.1 yrs
Completion rate29%
Withdrawal rate71%

Connectivity

Nearest IXPScaleMatrix Dallas Data Center US-South 01
IXP distance49.2 mi
Fiber providers5
Fiber coverage19.6%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance75.4 mi

Site characteristics

Parcel ownerOKLAHOMA GAS & ELECTRIC CO
Land owner typeprivate
Buildability60.0/100

Risk & environment

Flood zoneZone X
Water stress (WRI)1.80
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score58/100
Construction cost index73.4 (avg 100)

Location context

Nearest datacenterChoctaw Nation of Oklahoma Data Center
DC distance10.2 mi
Nearest rail3.4 mi
Nearest gas pipeline1.8 mi
Nearest fiber route13.6 mi
County hazard (FEMA NRI)Relatively High (42)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.04¢/kWh
Industrial electricity5.63¢/kWh
Cooling degree days1,900
Heating degree days3,600
Land price / acre$2,928

Incentive detail: Sales tax exemption on DC equipment; 5-year ad valorem tax exemption.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
56
Fiber connectivity12%
47
Energy cost10%
92
Water risk8%
64
Natural hazard8%
58
Buildability7%
60
Labor market4%
50
DC cluster4%
90
Land / acreage3%
51
Construction cost3%
89
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
30

Nearby comparable sites

Other scored datacenter candidate sites in Bryan County, ranked by DC Readiness.

Sites near UNKNOWN118766
SiteTypeVoltageCapacityQueue waitScore
CLEVELANDSubstation-Adjacent345 kV600 MW3.4 yrs70.4
UNKNOWN118773Substation-Adjacent138 kV100 MW3.4 yrs67.2
UNKNOWN175146Substation-Adjacent138 kV100 MW3.4 yrs67.0
UNKNOWN118774Substation-Adjacent138 kV100 MW3.4 yrs66.7
Greenfield (KIAMICHI STATION - UNKNOWN3013)Greenfield345 kV600 MW3.4 yrs66.5
UNKNOWN118772Substation-Adjacent138 kV100 MW3.4 yrs66.4
TAP141988Substation-Adjacent138 kV100 MW3.4 yrs66.2
Greenfield (HUGO (345 KV) - SUNNYSIDE)Greenfield345 kV600 MW3.4 yrs65.8

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNKNOWN118766, Bryan County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.