UNKNOWN137331

Substation-Adjacent

Hardin County, Ohio · PJM

DC Readiness
67.0
Good / 100

UNKNOWN137331 is a substation-adjacent datacenter candidate site in Hardin County, Ohio, interconnecting through PJM. It screens at 67.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.2 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN137331
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_AEP
Wholesale LMP$41.99/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth9
Avg queue wait3.2 yrs
Recent queue wait4.4 yrs
Completion rate17%
Withdrawal rate83%

Connectivity

Nearest IXPExpedient Columbus - Dublin
IXP distance43.3 mi
Fiber providers6
Fiber coverage65.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance55.1 mi

Site characteristics

Parcel ownerOhio Power
Parcel APN041200300000
Land owner typeprivate
Buildability65.0/100
Land cover (NLCD)Cultivated Crops

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteMCCULLOUGH INDUSTRIES
Hazard sub-score60/100
Construction cost index56.9 (avg 100)

Location context

Nearest datacenterAmazon Web Services
DC distance38.9 mi
Nearest rail0.6 mi
Nearest gas pipeline0.4 mi
Nearest fiber route67.7 mi
County hazard (FEMA NRI)Relatively Moderate (30)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.75¢/kWh
Industrial electricity8.80¢/kWh
Cooling degree days900
Heating degree days5,400
Land price / acre$9,197

Incentive detail: DC sales tax exemption on equipment and electricity (2022 law); JobsOhio grants.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
51
Fiber connectivity12%
68
Energy cost10%
91
Water risk8%
91
Natural hazard8%
60
Buildability7%
65
Labor market4%
50
DC cluster4%
50
Land / acreage3%
40
Construction cost3%
100
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
80

Nearby comparable sites

Other scored datacenter candidate sites in Hardin County, ranked by DC Readiness.

Sites near UNKNOWN137331
SiteTypeVoltageCapacityQueue waitScore
TAP140023Substation-Adjacent138 kV100 MW3.2 yrs70.0
Greenfield (MARYSVILLE - SOUTHWEST LIMA)Greenfield345 kV600 MW3.2 yrs67.0
Greenfield (MARYSVILLE - SOUTHWEST LIMA)Greenfield345 kV600 MW3.2 yrs66.5
Greenfield (MARYSVILLE - EAST LIMA SUBSTAT)Greenfield345 kV600 MW3.2 yrs66.4
Greenfield (MARYSVILLE - EAST LIMA SUBSTAT)Greenfield345 kV600 MW3.2 yrs66.2
Greenfield (MARYSVILLE - SOUTHWEST LIMA)Greenfield345 kV600 MW3.2 yrs66.0
Greenfield (MARYSVILLE - EAST LIMA SUBSTAT)Greenfield345 kV600 MW3.2 yrs64.1
Greenfield (UNKNOWN137331 - TAP140023)Greenfield138 kV100 MW3.2 yrs61.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.