UNKNOWN117895

Substation-Adjacent

Jefferson County, Missouri · PJM

DC Readiness
63.1
Good / 100

UNKNOWN117895 is a substation-adjacent datacenter candidate site in Jefferson County, Missouri, interconnecting through PJM. It screens at 63.1/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN117895
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.11¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPCogent St Louis
IXP distance25.9 mi
Fiber providers4
Fiber coverage31.4%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance285.6 mi

Site characteristics

Parcel ownerUNION ELECTRIC CO - (MO)
Land owner typeprivate
Buildability45.0/100
Land cover (NLCD)Deciduous Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteTHOMAS INDUSTRIAL COATINGS INC
Hazard sub-score52/100
Construction cost index85.9 (avg 100)

Location context

Nearest datacenterGenome Data Center
DC distance26.0 mi
Nearest rail0.7 mi
Nearest gas pipeline1.1 mi
Nearest fiber route215.7 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity10.54¢/kWh
Industrial electricity7.73¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$5,915

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
44
Fiber connectivity12%
63
Energy cost10%
93
Water risk8%
92
Natural hazard8%
52
Buildability7%
45
Labor market4%
50
DC cluster4%
60
Land / acreage3%
61
Construction cost3%
78
Gas pipeline2%
97
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Jefferson County, ranked by DC Readiness.

Sites near UNKNOWN117895
SiteTypeVoltageCapacityQueue waitScore
TAP139428Substation-Adjacent345 kV600 MW4.6 yrs69.8
TAP139427Substation-Adjacent345 kV600 MW4.6 yrs67.1
UNKNOWN117702Substation-Adjacent138 kV100 MW4.6 yrs66.8
TAP139434Substation-Adjacent138 kV100 MW4.6 yrs66.2
Greenfield (TAP139427 - TYSON)Greenfield345 kV600 MW4.6 yrs64.5
UNKNOWN121748Substation-Adjacent138 kV100 MW4.6 yrs63.8
Greenfield (TYSON - GRAY SUMMIT)Greenfield345 kV600 MW4.6 yrs62.2
TAP139432Substation-Adjacent138 kV100 MW4.6 yrs62.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.