UNKNOWN117557

Substation-Adjacent

Christian County, Missouri · MISO

DC Readiness
64.6
Good / 100

UNKNOWN117557 is a substation-adjacent datacenter candidate site in Christian County, Missouri, interconnecting through MISO. It screens at 64.6/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN117557
Substation distance0.0 mi
Substation voltage161 kV
Available capacity100 MW
LMP zoneMISO_ILLINOIS
Wholesale LMP$33.26/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth34
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPBluebird Underground Data Center
IXP distance7.9 mi
Fiber providers6
Fiber coverage29.8%
Nearest cloud providerGCP
Nearest cloud regionus-central1
Cloud region distance319.8 mi

Site characteristics

Parcel ownerCITY UTILITIES OF SPRINGFIELD - (MO)
Land owner typeprivate
Buildability100.0/100
Land cover (NLCD)Developed, High Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.60
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteBLOUNT FARM LAWN INC
Hazard sub-score52/100
Construction cost index74.5 (avg 100)

Location context

Nearest datacenterBluebird Underground Data Center
DC distance7.9 mi
Nearest rail2.3 mi
Nearest gas pipeline0.3 mi
Nearest fiber route83.0 mi
County hazard (FEMA NRI)Relatively High (38)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.80¢/kWh
Industrial electricity9.31¢/kWh
Cooling degree days1,500
Heating degree days4,700
Land price / acre$5,535

Incentive detail: Qualified data center sales tax exemption (2019 law); state income tax credits.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
60
Speed to power15%
48
Fiber connectivity12%
33
Energy cost10%
91
Water risk8%
88
Natural hazard8%
52
Buildability7%
100
Labor market4%
50
DC cluster4%
80
Land / acreage3%
46
Construction cost3%
88
Gas pipeline2%
99
Tax incentive2%
100
Climate / cooling2%
50

Nearby comparable sites

Other scored datacenter candidate sites in Christian County, ranked by DC Readiness.

Sites near UNKNOWN117557
SiteTypeVoltageCapacityQueue waitScore
James River Power StationBrownfield345 kV253 MW1.4 yrs67.5
UNKNOWN117508Substation-Adjacent161 kV100 MW1.4 yrs67.2
UNKNOWN121725Substation-Adjacent161 kV100 MW1.4 yrs66.8
UNKNOWN121724Substation-Adjacent161 kV100 MW1.4 yrs66.1
NIXA SOLAR, LLCSubstation-Adjacent161 kV100 MW1.4 yrs64.8
UNKNOWN121723Substation-Adjacent161 kV100 MW1.4 yrs64.7
TAP153768Substation-Adjacent161 kV100 MW1.4 yrs63.6
Greenfield (UNKNOWN117836 - UNKNOWN122479)Greenfield161 kV100 MW1.4 yrs62.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.