UNION, Mississippi · MISO

DC Readiness
71.2
Excellent / 100

UNION is a substation-adjacent datacenter candidate site in UNION, Mississippi, interconnecting through MISO. It screens at 71.2/100 DC Readiness with a catalogued 1,000 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNION
Substation distance0.0 mi
Substation voltage500 kV
Available capacity1,000 MW
LMP zoneMISO_MS
Wholesale LMP$31.68/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth13
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPC Spire Mississippi
IXP distance63.3 mi
Fiber providers9
Fiber coverage99.9%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance469.6 mi

Site characteristics

Parcel ownerScp Llc
Parcel APN007B-15-011.00
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index63.5 (avg 100)

Location context

Nearest datacenterC Spire Mississippi
DC distance63.3 mi
Nearest rail0.8 mi
Nearest gas pipeline8.7 mi
Nearest fiber route192.2 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.81¢/kWh
Industrial electricity6.91¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$2,286

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
100
Speed to power15%
59
Fiber connectivity12%
68
Energy cost10%
90
Water risk8%
90
Natural hazard8%
55
Buildability7%
40
Labor market4%
50
DC cluster4%
20
Land / acreage3%
52
Construction cost3%
97
Gas pipeline2%
72
Tax incentive2%
100
Climate / cooling2%
5

Nearby comparable sites

Other scored datacenter candidate sites in UNION, ranked by DC Readiness.

Sites near UNION
SiteTypeVoltageCapacityQueue waitScore
PLEASANT HILLSubstation-Adjacent500 kV1,000 MW1.4 yrs76.6
UNKNOWN111021Substation-Adjacent161 kV100 MW1.4 yrs68.4
TAP149912Substation-Adjacent161 kV100 MW1.4 yrs67.1
TAP149495Substation-Adjacent161 kV100 MW1.4 yrs66.6
NEW ALBANYSubstation-Adjacent161 kV100 MW1.4 yrs66.5
TAP149914Substation-Adjacent161 kV100 MW1.4 yrs65.4
TAP149909Substation-Adjacent161 kV100 MW1.4 yrs64.6
UNKNOWN111016Substation-Adjacent161 kV100 MW1.4 yrs64.4

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for UNION, UNION. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.