TAP142806 is a substation-adjacent datacenter candidate site in Jackson County, Mississippi, interconnecting through MISO. It screens at 60.9/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP142806
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneMISO_MS
Wholesale LMP$31.68/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth13
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPEdgeConneX New Orleans (EDCSLI01)
IXP distance73.3 mi
Fiber providers6
Fiber coverage87.7%
Nearest cloud providerGCP
Nearest cloud regionus-south1
Cloud region distance514.6 mi

Site characteristics

Parcel ownerWhitehead John J (Est)
Parcel APN759.31-04-0013.00
Land owner typeprivate
Buildability15.0/100
Land cover (NLCD)Woody Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteWALMART SUPERCENTER 1066
Hazard sub-score45/100
Construction cost index85.6 (avg 100)

Location context

Nearest datacenterEdgeConneX New Orleans (EDCSLI01)
DC distance73.3 mi
Nearest rail0.1 mi
Nearest gas pipeline1.8 mi
Nearest fiber route96.3 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.64¢/kWh
Industrial electricity8.46¢/kWh
Cooling degree days2,400
Heating degree days2,400
Land price / acre$5,657

Incentive detail: Sales tax exemption on DC equipment for $50M+ investments; fee-in-lieu of property tax.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
59
Fiber connectivity12%
75
Energy cost10%
90
Water risk8%
90
Natural hazard8%
45
Buildability7%
15
Labor market4%
50
DC cluster4%
20
Land / acreage3%
61
Construction cost3%
79
Gas pipeline2%
94
Tax incentive2%
100
Climate / cooling2%
5

Nearby comparable sites

Other scored datacenter candidate sites in Jackson County, ranked by DC Readiness.

Sites near TAP142806
SiteTypeVoltageCapacityQueue waitScore
DANIEL STATIONSubstation-Adjacent500 kV1,000 MW1.4 yrs73.8
UNKNOWN110550Substation-Adjacent230 kV300 MW1.4 yrs70.5
UNKNOWN110319Substation-Adjacent230 kV300 MW1.4 yrs66.9
TAP142799Substation-Adjacent115 kV100 MW1.4 yrs66.7
TAP142801Substation-Adjacent115 kV100 MW1.4 yrs65.5
UNKNOWN110550Substation-Adjacent230 kV300 MW1.4 yrs65.2
Greenfield (MC KNIGHT - DANIEL STATION)Greenfield500 kV1,000 MW1.4 yrs65.1
Greenfield (BIG CREEK - DANIEL STATION)Greenfield500 kV1,000 MW1.4 yrs65.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP142806, Jackson County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.