Datacenter Sites in Winona, Minnesota
Winona has 19 scored datacenter candidate sites averaging 56.5/100 DC Readiness, with a catalogued aggregate of 2,100 MW. FEMA rates local natural-hazard risk as "Relatively Moderate". The county has a datacenter tax incentive on record.
19
Candidate sites
56.5/100
Avg DC Readiness
2,100 MW
Catalogued capacity
theoretical aggregate
Relatively Moderate
Hazard rating
Site-selection context for Winona
Yessales_tax_exemption
Datacenter tax incentive
12.87¢/kWh
Commercial electricity
9.31¢/kWh
Industrial electricity
4
Fiber providers
Low
Water stress
$6,840
Land price / acre
600
Cooling degree days
7,700
Heating degree days
42°F
Mean annual temp
Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.
By site type
Top datacenter sites in Winona
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| OZ Winona | Greenfield | — | — | 1.4 yrs | 63.9 |
| TAP139558 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 55.5 |
| UNKNOWN157990 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 55.0 |
| TAP171256 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 55.0 |
| St. Charles - Chattanooga Innovation Park | Shovel-Ready | — | — | 2.8 yrs | 54.7 |
| Greenfield (NORTH ROCHESTER - BRIGGS ROAD) | Greenfield | 345 kV | 600 MW | 2.8 yrs | 54.4 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 54.1 |
| TAP158819 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 54.1 |
| UNKNOWN131058 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 54.1 |
| TAP158812 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 53.9 |
| TAP158820 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 53.9 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 53.8 |
| UNKNOWN157983 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 53.7 |
| UNKNOWN156610 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 53.7 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 53.7 |
| UNKNOWN131554 | Substation-Adjacent | 161 kV | 100 MW | 2.8 yrs | 53.5 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 53.0 |
| Wilson - WAIDA Acres | Shovel-Ready | — | — | 2.8 yrs | 53.0 |
| Mine Site | Former Mine | — | — | 2.8 yrs | 52.6 |
| GOODVIEW | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| TAP158817 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN157986 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| TAP158816 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| UNKNOWN129251 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
| TAP139580 | Substation-Adjacent | 69 kV | 50 MW | 2.8 yrs | 52.4 |
Winona datacenter FAQ
- How many datacenter sites are in Winona?
- 19 scored datacenter candidate sites, averaging 56.5/100 DC Readiness.
- Does Winona offer datacenter tax incentives?
- Sales tax exemption on DC equipment and electricity for qualified DCs.
- What is the natural-hazard risk in Winona?
- FEMA's National Risk Index rates Winona as "Relatively Moderate" (score 25).
- What are industrial electricity rates in Winona?
- Average industrial electricity is 9.31¢/kWh and commercial is 12.87¢/kWh in Winona.
Dataset updated . Screening estimates derived from public data sources.