Sherburne, Minnesota · MISO

DC Readiness
74.7
Excellent / 100

ELK RIVER is a substation-adjacent datacenter candidate site in Sherburne, Minnesota, interconnecting through MISO. It screens at 74.7/100 DC Readiness with a catalogued 300 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationELK RIVER
Substation distance0.0 mi
Substation voltage230 kV
Available capacity300 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPDataBank Minneapolis (MSP3)
IXP distance13.0 mi
Fiber providers9
Fiber coverage23.8%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance236.0 mi

Site characteristics

Parcel ownerNORTHERN STATES POWER CO - MINNESOTA
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteLEES RIVERSIDE AUTO INC
Hazard sub-score65/100
Construction cost index94.7 (avg 100)

Location context

Nearest datacenterDataBank
DC distance13.0 mi
Nearest rail1.9 mi
Nearest gas pipeline4.0 mi
Nearest fiber route230.4 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.94¢/kWh
Industrial electricity9.05¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$7,181

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
78
Speed to power15%
57
Fiber connectivity12%
71
Energy cost10%
86
Water risk8%
90
Natural hazard8%
65
Buildability7%
92
Labor market4%
50
DC cluster4%
80
Land / acreage3%
52
Construction cost3%
71
Gas pipeline2%
87
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Sherburne, ranked by DC Readiness.

Sites near ELK RIVER
SiteTypeVoltageCapacityQueue waitScore
SHERBURNE COUNTYSubstation-Adjacent345 kV600 MW1.4 yrs71.9
MONTICELLOSubstation-Adjacent345 kV600 MW1.4 yrs70.3
UNKNOWN132179Substation-Adjacent115 kV100 MW1.4 yrs68.8
UNKNOWN129671Substation-Adjacent115 kV100 MW1.4 yrs66.0
Greenfield (MONTICELLO - QUARRY)Greenfield345 kV600 MW1.4 yrs65.9
Greenfield (MONTICELLO - BENTON)Greenfield230 kV300 MW1.4 yrs65.1
EC Near Elk River City ofGreenfield1.4 yrs64.7
EC Near Elk River City ofGreenfield1.4 yrs64.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for ELK RIVER, Sherburne. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.