UNKNOWN132020

Substation-Adjacent

Nicollet County, Minnesota · MISO

DC Readiness
62.8
Good / 100

UNKNOWN132020 is a substation-adjacent datacenter candidate site in Nicollet County, Minnesota, interconnecting through MISO. It screens at 62.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 1.4 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN132020
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
LMP zoneMISO_MINN
Wholesale LMP$34.82/MWh
Utility commercial rate0.13¢/kWh

Speed to power

ISO / RTO regionMISO
Queue depth16
Avg queue wait1.4 yrs
Recent queue wait1.4 yrs
Completion rate18%
Withdrawal rate82%

Connectivity

Nearest IXPNP Belle Plaine (MSP1)
IXP distance33.0 mi
Fiber providers9
Fiber coverage60.8%
Nearest cloud providerAzure
Nearest cloud regioncentralus
Cloud region distance175.5 mi

Site characteristics

Parcel ownerNORTHERN STATES POWER CO - MINNESOTA
Land owner typeprivate
Buildability20.0/100
Land cover (NLCD)Emergent Herbaceous Wetlands

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteHEWITT MACHINE MANUFACTURING
Hazard sub-score65/100
Construction cost index88.8 (avg 100)

Location context

Nearest datacenterNP Belle Plaine (MSP1)
DC distance33.0 mi
Nearest rail4.4 mi
Nearest gas pipeline8.5 mi
Nearest fiber route64.1 mi
County hazard (FEMA NRI)Relatively Moderate (25)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity12.59¢/kWh
Industrial electricity9.61¢/kWh
Cooling degree days600
Heating degree days7,700
Land price / acre$8,617

Incentive detail: Sales tax exemption on DC equipment and electricity for qualified DCs.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
57
Fiber connectivity12%
64
Energy cost10%
86
Water risk8%
92
Natural hazard8%
65
Buildability7%
20
Labor market4%
50
DC cluster4%
45
Land / acreage3%
41
Construction cost3%
76
Gas pipeline2%
73
Tax incentive2%
100
Climate / cooling2%
95

Nearby comparable sites

Other scored datacenter candidate sites in Nicollet County, ranked by DC Readiness.

Sites near UNKNOWN132020
SiteTypeVoltageCapacityQueue waitScore
UNKNOWN129725Substation-Adjacent115 kV100 MW1.4 yrs67.1
Greenfield (UNKNOWN132020 - WILMARTH)Greenfield115 kV100 MW1.4 yrs61.5
Greenfield (UNKNOWN129725 - UNKNOWN132020)Greenfield115 kV100 MW1.4 yrs56.9
Mine SiteFormer Mine43.8
Schmidt's Meat Market ExpansionIndustrial39.1

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.