Datacenter Sites in Reno County, Kansas
Reno County has 36 scored datacenter candidate sites averaging 56.4/100 DC Readiness, with a catalogued aggregate of 2,253 MW. FEMA rates local natural-hazard risk as "Relatively High". The county has a datacenter tax incentive on record.
36
Candidate sites
56.4/100
Avg DC Readiness
2,253 MW
Catalogued capacity
theoretical aggregate
Relatively High
Hazard rating
Site-selection context for Reno County
Yesproperty_tax_exemption
Datacenter tax incentive
10.97¢/kWh
Commercial electricity
8.41¢/kWh
Industrial electricity
6
Fiber providers
Medium-High
Water stress
$2,641
Land price / acre
1,400
Cooling degree days
5,000
Heating degree days
55°F
Mean annual temp
Incentive detail: PEAK program payroll tax incentives; IRB property tax exemptions available.
By site type
Top datacenter sites in Reno County
| Site | Type | Voltage | Capacity | Queue wait | Score |
|---|---|---|---|---|---|
| OZ Reno | Greenfield | — | — | 3.5 yrs | 60.6 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 59.6 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 59.3 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 58.3 |
| RENO | Substation-Adjacent | 345 kV | 600 MW | 3.3 yrs | 58.3 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 58.1 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 58.0 |
| UNKNOWN118040 | Substation-Adjacent | 230 kV | 300 MW | 3.3 yrs | 57.8 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 57.4 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 55.9 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 55.7 |
| EC Near Hutchinson Energy Center | Greenfield | — | — | 3.5 yrs | 54.4 |
| UNKNOWN119865 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.8 |
| TAP138841 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.8 |
| UNKNOWN119868 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| UNKNOWN118026 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| UNKNOWN172444 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| UNKNOWN119866 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| UNKNOWN118038 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| UNKNOWN119867 | Substation-Adjacent | 115 kV | 100 MW | 3.3 yrs | 52.0 |
| Liberty Homes BTA | Industrial | — | — | 3.3 yrs | 50.6 |
| Lighthouse Landing Rv Park BTA | Industrial | — | — | 3.3 yrs | 50.4 |
| Greenfield (UNKNOWN118040 - UNKNOWN118044) | Greenfield | 230 kV | 300 MW | 3.3 yrs | 50.1 |
| TAP168679 | Substation-Adjacent | 69 kV | 50 MW | 3.3 yrs | 50.0 |
| TAP168676 | Substation-Adjacent | 69 kV | 50 MW | 3.3 yrs | 50.0 |
Reno County datacenter FAQ
- How many datacenter sites are in Reno County?
- 36 scored datacenter candidate sites, averaging 56.4/100 DC Readiness.
- Does Reno County offer datacenter tax incentives?
- PEAK program payroll tax incentives; IRB property tax exemptions available.
- What is the natural-hazard risk in Reno County?
- FEMA's National Risk Index rates Reno County as "Relatively High" (score 35).
- What are industrial electricity rates in Reno County?
- Average industrial electricity is 8.41¢/kWh and commercial is 10.97¢/kWh in Reno County.
Dataset updated . Screening estimates derived from public data sources.