UNKNOWN125461

Substation-Adjacent

SCOTT, Indiana · PJM

DC Readiness
64.5
Good / 100

UNKNOWN125461 is a substation-adjacent datacenter candidate site in SCOTT, Indiana, interconnecting through PJM. It screens at 64.5/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationUNKNOWN125461
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPHeyburn Building
IXP distance31.3 mi
Fiber providers4
Fiber coverage67.1%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance172.1 mi

Site characteristics

Parcel ownerDUKE ENERGY INDIANA INC
Land owner typeprivate
Buildability95.0/100
Land cover (NLCD)Developed, Medium Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteFAMILY DOLLAR 1095
Hazard sub-score58/100
Construction cost index64.3 (avg 100)

Location context

Nearest datacenterHeyburn Building
DC distance31.3 mi
Nearest rail0.2 mi
Nearest gas pipeline21.0 mi
Nearest fiber route86.3 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.75¢/kWh
Industrial electricity9.80¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$6,850

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
35
Fiber connectivity12%
68
Energy cost10%
89
Water risk8%
89
Natural hazard8%
58
Buildability7%
95
Labor market4%
50
DC cluster4%
45
Land / acreage3%
44
Construction cost3%
96
Gas pipeline2%
33
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in SCOTT, ranked by DC Readiness.

Sites near UNKNOWN125461
SiteTypeVoltageCapacityQueue waitScore
Greenfield (JEFFERSON - ROCKPORT STATION)Greenfield765 kV1,000 MW4.6 yrs68.6
Greenfield (JEFFERSON - ROCKPORT STATION)Greenfield765 kV1,000 MW4.6 yrs67.5
Greenfield (R GALLAGHER - COLUMBUS (345KV))Greenfield230 kV300 MW3.0 yrs62.0
Greenfield (JEFFERSON - ROCKPORT STATION)Greenfield765 kV1,000 MW4.6 yrs61.5
Greenfield (UNKNOWN124908 - COLUMBUS (345K)Greenfield230 kV300 MW3.0 yrs59.2
Greenfield (UNKNOWN124899 - UNKNOWN125461)Greenfield138 kV100 MW3.0 yrs51.3
TECHNE ENGINEERING (MACHINE SHOPS)Manufacturing50.3
DERBY FABRICATING (ALL OTHER CONVERTED PAPER PRODUCT MANUFACTURING)Manufacturing50.0

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.