Montgomery County, Indiana · PJM

DC Readiness
66.0
Good / 100

SPANN AVE is a substation-adjacent datacenter candidate site in Montgomery County, Indiana, interconnecting through PJM. It screens at 66.0/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.0 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationSPANN AVE
Substation distance0.0 mi
Substation voltage138 kV
Available capacity100 MW
LMP zonePJM_DUKE
Wholesale LMP$41.74/MWh
Utility commercial rate0.12¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth56
Avg queue wait3.0 yrs
Recent queue wait4.2 yrs
Completion rate14%
Withdrawal rate87%

Connectivity

Nearest IXPWintek Corporation
IXP distance26.4 mi
Fiber providers8
Fiber coverage89.2%
Nearest cloud providerAzure
Nearest cloud regionnorthcentralus
Cloud region distance132.8 mi

Site characteristics

Parcel ownerDUKE ENERGY INDIANA, LLC
Land owner typeprivate
Buildability92.0/100
Land cover (NLCD)Developed, Low Intensity

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyPresent
Superfund siteSOMMER METALCRAFT CORPORATION
Hazard sub-score58/100
Construction cost index85.5 (avg 100)

Location context

Nearest datacenterWintek Corporation
DC distance26.4 mi
Nearest rail0.3 mi
Nearest gas pipeline16.4 mi
Nearest fiber route43.8 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity11.64¢/kWh
Industrial electricity8.72¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$8,819

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
58
Speed to power15%
35
Fiber connectivity12%
79
Energy cost10%
84
Water risk8%
90
Natural hazard8%
58
Buildability7%
92
Labor market4%
50
DC cluster4%
65
Land / acreage3%
56
Construction cost3%
79
Gas pipeline2%
47
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Montgomery County, ranked by DC Readiness.

Sites near SPANN AVE
SiteTypeVoltageCapacityQueue waitScore
NUCORSubstation-Adjacent345 kV600 MW3.0 yrs71.3
TAP138291Substation-Adjacent138 kV100 MW4.6 yrs66.9
UNKNOWN160174Substation-Adjacent138 kV100 MW3.0 yrs66.6
UNKNOWN124554Substation-Adjacent138 kV100 MW4.6 yrs66.4
UNKNOWN124554Substation-Adjacent138 kV100 MW3.0 yrs66.2
Greenfield (CAYUGA - NUCOR)Greenfield345 kV600 MW4.6 yrs65.9
UNKNOWN124403Substation-Adjacent138 kV100 MW3.0 yrs65.9
UNKNOWN124404Substation-Adjacent138 kV100 MW3.0 yrs64.7

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen