Dubois County, Indiana · PJM

DC Readiness
72.7
Excellent / 100

HE RAMSEY is a substation-adjacent datacenter candidate site in Dubois County, Indiana, interconnecting through PJM. It screens at 72.7/100 DC Readiness with a catalogued 600 MW of candidate capacity and a 4.6 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationHE RAMSEY
Substation distance0.0 mi
Substation voltage345 kV
Available capacity600 MW
LMP zonePJM_COMED
Wholesale LMP$33.95/MWh
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionPJM
Queue depth265
Avg queue wait4.6 yrs
Recent queue wait2.9 yrs
Completion rate21%
Withdrawal rate79%

Connectivity

Nearest IXPSITCO Evansville
IXP distance33.7 mi
Fiber providers8
Fiber coverage97.8%
Nearest cloud providerAWS
Nearest cloud regionus-east-2
Cloud region distance244.0 mi

Site characteristics

Parcel ownerSOUTHERN INDIANA GAS & ELEC CO
Land owner typeprivate
Buildability85.0/100
Land cover (NLCD)Barren Land

Risk & environment

Flood zoneZone X
Water stress (WRI)0.50
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score68/100
Construction cost index77.4 (avg 100)

Location context

Nearest datacenterSITCO Evansville
DC distance33.7 mi
Nearest rail1.9 mi
Nearest gas pipeline5.1 mi
Nearest fiber route122.9 mi
County hazard (FEMA NRI)Relatively Moderate (32)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity13.71¢/kWh
Industrial electricity9.46¢/kWh
Cooling degree days1,000
Heating degree days5,500
Land price / acre$7,380

Incentive detail: Sales tax exemption on DC equipment for $750M+/$400M+ investments; EDGE credits up to 100% of payroll taxes.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
87
Speed to power15%
44
Fiber connectivity12%
74
Energy cost10%
85
Water risk8%
90
Natural hazard8%
68
Buildability7%
85
Labor market4%
50
DC cluster4%
40
Land / acreage3%
43
Construction cost3%
86
Gas pipeline2%
84
Tax incentive2%
100
Climate / cooling2%
75

Nearby comparable sites

Other scored datacenter candidate sites in Dubois County, ranked by DC Readiness.

Sites near HE RAMSEY
SiteTypeVoltageCapacityQueue waitScore
ROCKPORT STATIONSubstation-Adjacent765 kV1,000 MW4.6 yrs72.9
DUFFSubstation-Adjacent345 kV600 MW4.6 yrs70.9
Greenfield (SULLIVAN - ROCKPORT STATION)Greenfield765 kV1,000 MW4.6 yrs69.0
Greenfield (HE RAMSEY - DUFF)Greenfield345 kV600 MW4.6 yrs66.8
Greenfield (JEFFERSON - ROCKPORT STATION)Greenfield765 kV1,000 MW4.6 yrs66.3
Greenfield (HE RAMSEY - DUFF)Greenfield345 kV600 MW4.6 yrs65.7
DEBOISSubstation-Adjacent138 kV100 MW3.0 yrs65.1
Greenfield (HE RAMSEY - DUFF)Greenfield345 kV600 MW4.6 yrs64.3

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.