Coffee County, Alabama · SERC

DC Readiness
61.8
Good / 100

TAP142982 is a substation-adjacent datacenter candidate site in Coffee County, Alabama, interconnecting through SERC. It screens at 61.8/100 DC Readiness with a catalogued 100 MW of candidate capacity and a 3.7 yrs average interconnection-queue wait.

Power & interconnection

Nearest substationTAP142982
Substation distance0.0 mi
Substation voltage115 kV
Available capacity100 MW
Utility commercial rate0.14¢/kWh

Speed to power

ISO / RTO regionSERC
Queue depth1
Avg queue wait3.7 yrs
Recent queue wait3.5 yrs
Completion rate15%
Withdrawal rate85%

Connectivity

Nearest IXPRSA Dexter Avenue Datacenter
IXP distance58.2 mi
Fiber providers7
Fiber coverage93.8%
Nearest cloud providerGCP
Nearest cloud regionus-east1
Cloud region distance371.2 mi

Site characteristics

Parcel ownerALABAMA POWER CO
Land owner typeprivate
Buildability40.0/100
Land cover (NLCD)Evergreen Forest

Risk & environment

Flood zoneZone X
Water stress (WRI)0.40
Wetlands (NWI)Clear
Critical habitatClear
Superfund nearbyClear
Hazard sub-score55/100
Construction cost index64.5 (avg 100)

Location context

Nearest datacenterAngelTrax Data Center
DC distance42.8 mi
Nearest rail11.0 mi
Nearest gas pipeline53.6 mi
Nearest fiber route2.0 mi
County hazard (FEMA NRI)Relatively High (45)
DC tax incentiveYes (sales_tax_exemption)
Commercial electricity14.45¢/kWh
Industrial electricity9.53¢/kWh
Cooling degree days2,100
Heating degree days2,800
Land price / acre$3,859

Incentive detail: Sales & use tax abatement on qualifying equipment. $400M+ investment threshold.

Full DC Readiness breakdown

All 13 weighted sub-scores (0–100) behind the composite DC Readiness score.

Power availability20%
56
Speed to power15%
66
Fiber connectivity12%
62
Energy cost10%
85
Water risk8%
89
Natural hazard8%
55
Buildability7%
40
Labor market4%
50
DC cluster4%
40
Land / acreage3%
49
Construction cost3%
96
Gas pipeline2%
0
Tax incentive2%
100
Climate / cooling2%
20

Nearby comparable sites

Other scored datacenter candidate sites in Coffee County, ranked by DC Readiness.

Sites near TAP142982
SiteTypeVoltageCapacityQueue waitScore
TAP168970Substation-Adjacent115 kV100 MW3.7 yrs68.6
TAP168972Substation-Adjacent115 kV100 MW3.7 yrs67.0
TAP155677Substation-Adjacent115 kV100 MW3.7 yrs66.5
TAP168974Substation-Adjacent115 kV100 MW3.7 yrs65.9
UNKNOWN109315Substation-Adjacent115 kV100 MW3.7 yrs65.8
Greenfield (PINCKARD - OPP)Greenfield230 kV300 MW3.7 yrs65.6
UNKNOWN109316Substation-Adjacent115 kV100 MW3.7 yrs65.1
TAP159882Substation-Adjacent115 kV100 MW3.7 yrs63.2

Dataset updated . Screening estimates derived from public data sources.

Figures are screening estimates derived from public infrastructure data. Catalogued capacity reflects theoretical candidate capacity, not deliverable or committed interconnection. Confirm all values with the utility, ISO, and on-the-ground due diligence.

Go deeper than the public screen

This page shows a public slice of the GridCensus dataset for TAP142982, Coffee County. Pro and Enterprise plans unlock the full 164,098-site catalog, raw sub-scores, parcel ownership, interconnection-queue detail, saved searches, and programmatic API access.